Home » Projects » Subsidence Solution for blocks of flats – Oxford City Council

Background

Clay shrinkage subsidence, exacerbated by tree root influence, had caused significant subsidence damage to two neighbouring blocks of flats in Oxford. It is considered the damage commenced during the severe summer drought of 2018, with further movement during the dry summer of 2019. The damage was considered progressive and seasonal.

Site Investigations were instigated, confirming both desiccated clay and the presence of tree roots to around 3.1m below ground level. Concrete strip foundations founded at 1.2m below ground were confirmed to be 0f 0.7m thickness.

The damage was localised, affecting corners of both blocks of flats, with typical subsidence cracking to internal and external masonry walls. Additionally, an internal section of the floor slab had dropped.

 

Customer alternatives

Oxford City Council fully considered the most viable and economic solutions available to arrest the movement, allowing superstructure repairs to commence. The solution required speed of design, a lack of disruption for the multiple tenants, short on-site duration and economic benefits.

Potential schemes utilising traditional underpinning or piling techniques would involve significant excavations and disruption, lengthy on-site duration, and added overall cost. With around 35 linear meters of foundations requiring stabilisation, outline costs for underpinning or piling were in the region of £65,000, excluding requirements for alternative accommodation.

 

Why Geobear

Geobear presented a fully engineered scheme and quotation within 2 weeks of instruction. The design allowed for a total of 5 days on-site, with minimal enabling work, and no requirement to decant any tenants. Site Investigations, drain surveys and enabling work were all arranged by Geobear as part of the project.

The non-disruptive solution did not require any excavation or landscaping work on completion. 

 

Insertion of injection tubes in preparation for injection

Geobear solution

Across the two blocks, the design included stabilisation of 34 linear meters of strip foundations and stabilisation/lift of the damaged floor slab.

Enabling works were limited to some local exposing of services to enable safe drilling and temporary relocation of an ornamental planter.

Specialist clay geopolymers were injected into the ground at specified 

Drain monitoring

locations. Laser levels were used to closely monitor all injection sequences, to ensure geopolymer filled all voids and fissures and met the underside of foundations. The geopolymer, specifically designed for clay soils increases the load-bearing strength of the soil and eliminates the harmful effects of shrink / swell seasonal movement.

During the drilling and injection works, drainage monitoring was carried out to ensure there was no damage to drain runs or material ingress.

During the works, unforeseen soil conditions were discovered, with localised pockets of solid lime interspersed within the clay. Geobear worked up design revisions on-site, liaising closely with the client throughout. Neither the programme of work nor the overall cost were affected.

Contact Us

Please use this contact form or navigate to the contact us page and send us a message. We will respond to you within 24hrs.

Alternatively please call us on 0800 084 3503 and speak to our customer services team. Calling from Ireland please go to the contact us page.

We deliver projects on any sort of building or structure – from conservatory extension problems to 80,000m2 warehouses and road infrastructure. In most cases we will have the best solution, so get in touch today.

  • This field is for validation purposes and should be left unchanged.