Home » Projects » Re-levelling: Slab lifting bottling plant

Major bottling facility in South West England

Geobear were brought in to relevel the floor of a major industrial building whilst allowing it to remain fully operational.

In South West England one of Europe’s largest, newly constructed, bottling facilities had become subject to the effects of settlement. The implications of the settlement were to have far-reaching consequences for all the stakeholders involved in the original construction and the incumbent tenant.

The facility in question is over 80,000 m2 and the problems began after the tenant moved in and commenced operations. As the facility was loaded it began to experience significant slab settlement making the entire facility unstable. The maximum settlement experienced on site was 36mm.

bottling facilty drawingWe designed a solution based on the level survey drawings which would relevel the slabs, bringing them back to within 4mm from the original spec. The process involved injection of geopolymers beneath the slab across the facility which would raise and relevel the floor.

In terms of our ground engineering process, we designed a programme of work based upon the site drawings that would require three passes; meaning that we would inject the areas that showed the greatest drop in level first, we’d repeat that process on the same area and all other areas that had a slightly lower level of settlement and finally a third pass where all areas would be treated to bring all the slabs back to within 4mm of their required levels.

For this project, we designed small purpose-built mobile pumping units that would fit within the aisles of the facility and meet all health and safety criteria. This crucially allowed the business operations to continue unaffected in aisles adjacent to where we worked and as our process only requires electricity to power the pumps, there were no environmental or hazardous implications.

As we went through the process of ground injection, we substantiated every lift using laser monitoring. In order to verify those levels, an independent surveyor was also contracted to conduct additional monitoring.

Our process has secured the future of the facility and our fast, isolated treatment programme ensure operations could continue unabated. Due to the excessively weak ground soils, however, this particular facility floor will continue to move as a permanent solution was not viable; consequently, there will be six-monthly assessments for future treatment with Uretek on standby to relevel where necessary.

 


 

Homeowner Contact Form

  • This will help us as we can look at local site conditions.
  • This field is for validation purposes and should be left unchanged.

Contact Us

Please use this contact form or navigate to the contact us page and send us a message. We will respond to you within 24hrs.

Alternatively please call us on 0800 084 3503 and speak to our customer services team. Calling from Ireland please go to the contact us page.

We deliver projects on any sort of building or structure – from conservatory extension problems to 80,000m2 warehouses and road infrastructure. In most cases we will have the best solution, so get in touch today.

  • This field is for validation purposes and should be left unchanged.